Hydraulic installation in our holiday cabins

Instalacja hydrauliczna w naszych domkach
October 18, 2018
Drewnolandia
Guide

HYDRAULIC INSTALLATION WITH BOILER

Installation components



1. Routing of pipes from the water supply connection brought and brought above the foundation level by the investor, to water draw-off points in the wall. The number of these points is 5. Standardly 3 in the bathroom (water supply to the sink, toilet and shower) and one in the kitchen (water supply to the sink) and one under the boiler or water heater.

2. Routing of the water installation with a slope enabling water to be drained for the winter.

3. Installation of the Ariston Velis Evo 80 boiler with a 65-liter capacity and a heating element.

4. The installation is performed using PEX pipes and fittings.

5. The recommended diameter of the service pipe to be carried out by the investor is 32mm; if a different diameter is required the investor is obliged to inform the contractor of the changes.

6. Recommended sewer pipe diameters for the investor to install: 100mm for the toilet, the others 50mm; if a different diameter is needed the investor must inform the contractor of the changes.


The hydraulic installation does not include:



- laying the water connection to the cabin (water must be brought to the foundation and brought above its level by the installation day)
- installation of fixtures
- installation of washbasins, taps, showers, bathtubs, etc.
- construction of drains

Installation diagram:



If a hydraulic installation and wall insulation with their finishing with paneling are ordered, the hydraulic installation is mounted in an additional horizontal installation frame of 4 cm thickness and is separated from the insulation by a vapor barrier. If only the installation is ordered without finishing with paneling, the hydraulic installation is mounted in the structural frame, without an additional installation frame.


Below is the schematic of the installation in the frame:

Electrical instructions


Electrical instructions

Recommendations for the investor



The onus is on the client to provide the sewer outlets in a minimum quantity of 4; all outlets must be brought above the foundation level at the target locations.

Standard arrangement looks as follows:
- bathroom, drain 100 to the toilet, 2 drains 50 to the shower and the washbasin

- kitchen – drain 50 to the sink


Belowexample*diagram for the layout of drains and the water connection for the standard version of the Julian model, 5.5m x 6m.

1. The shower drain should be located in the bathroom corner about 20 cm from the wall to the drain axis. After installing the tray there is then a possibility to connect it to the drain using elbows or a flexible connector.

2. The bathroom sink drain should be placed right against the wall.

3. The drain in the kitchenette should be located where the sink will ultimately be placed; this drain should also be right by the wall. This is also where we place the water supply to the cabin.

4. The toilet drain. We recommend preparing a drain for a toilet with a horizontal drain due to greater flexibility during fixture installation and the possibility of mounting a wall-hung Geberit toilet. The suggested distance of the toilet drain axis from the foundation edge should be between 20 cm and 25 cm (7 cm from the finished wall). The distance from the side wall to the foundation edge is about 55 cm (40 cm from the finished wall).

5. Water connection. The most convenient place to locate it is under the sink cabinet in the kitchenette, so it is hidden and we always have access to the valve.

6. Drains should protrude no more than 5 cm above the foundation slab level

* this is solely an example of the layout of drains and connections; do not rely on it when installing drains and connections for the cabin. A precise, dimensioned sketch of connections and drains is prepared individually for each project at the appropriate stage of ordering.

Electrical instruction 1



* this is solely an example of the layout of drains and connections; do not rely on it when installing drains and connections for the cabin. A precise, dimensioned sketch of connections and drains is prepared individually for each project at the appropriate stage of ordering.

Electrical instruction 2


Installation assembly instructions